The project involved the rehabilitation of infrastructure for infill plots at Delma (53 residential plots). The objective was to extend, modify, and upgrade all existing utilities, networks, and services to accommodate the new plots.
Construction Value: AED 87 million / EUR 21.75 million
The project involved the rehabilitation of infrastructure for infill plots at Mirfa (99 residential plots). The objective was to extend, modify, and upgrade all existing utilities, networks, and services to accommodate the new plots.
Construction Value: AED 60 million / EUR 15 million
The project involved the rehabilitation of infrastructure for infill plots at Silaa (104 residential plots). The objective was to extend, modify, and upgrade all existing utilities, networks, and services to accommodate the new plots.
Construction Value: AED 80 million / EUR 20 million