KN International has been requested to provide the infrastructure master plan for Ruwais as part of the UPC “Plan Al Gharbia 2030”. It is designed to help Al Gharbia to evaluate and respond to current and future development needs and to introduce a comprehensive set of policies for development of the region and its individual communities.

The objective of the utility master plan is to provide a conceptual framework of various infrastructure networks necessary to service the community.
Coordination with the local utility authorities has occurred during the preparation of this master plan to ensure an acceptable concept.

The following tasks are some of the services provided by KN:

Data collection and detailed infrastructure master planning of the following:
- 210km of sewage pipelines ranging from 150-900mm diameter, 6,000 numbers
of manholes, 1 permanent sewage treatment plant (STP) and 3 temporary STP - 245km of storm water drainage pipelines ranging from 300-2,500mm diameter,
9,800 numbers of manholes and 11,700 gullies - 145km of TSE and irrigation pipelines ranging from 110-800mm diameter, 4
reservoir, 1 irrigation pumping stations Close liaison with all concerned statutory authorities involved Preparation of drawings, schedules, cost estimates, design calculations, design guidelines etc.